Timetable
The project will take shape in the middle of the River Wear and on the north and south banks.
Here are some of the highlights:
May 2015
Contract awarded and design is underway
July 2015
Construction work started
October 2015
Construction work starts in the river
Winter 2015
12-month major improvement works start on A1231 Wessington Way
Summer 2016
Major improvement works start on B1405 European Way in Pallion
Winter 2016
A-frame pylon sets sail from Belgium and is lifted into place
Summer 2017
Bridge deck work is complete
28 August 2018
Northern Spire is open to pedestrians for one day before it is open to traffic. Approximately 20,000 people enjoy a walk over.
29 August 2018
Northern Spire opens to traffic.